Fictional worked example · Reusable template

Project risk register

Review date: November 6, 2026

Workshop registration opens November 16.

R-01OPEN

Room capacity may change

If the venue confirms fewer than 40 places, registration capacity or the session plan must change.

Already in place

Booking limit stays at zero until capacity is confirmed.

Current assessment

Possible: seating plan is not confirmed. Major: the registration offer could change.

Next action / accountable owner

Morgan: request written capacity confirmation by November 5.

Trigger / fallback

If unconfirmed November 6 at noon, Casey asks about a second session.

Next review: November 6. · Response assigned; confirmation outstanding.

R-02OPEN

Arrival instructions may be missing

The draft email has no entrance instructions; registrants could receive incomplete arrival information.

Already in place

Registration remains in test mode.

Current assessment

Possible: the entrance field is still empty. Moderate: staff would need to contact affected registrants.

Next action / accountable owner

Casey: add confirmed instructions and run a test registration by November 9.

Trigger / fallback

If the test email is incomplete, keep registration closed.

Next review: November 10. · Awaiting venue information.